The Haven II
Under constructionby Meraki Real Estate Development · Majan
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in The Haven II is AED 1.02M (AED 1,260 per sqft), 15% below the Majan median of AED 1,480 per sqft, from 62 sales in the last 12 months. It is 56% built, with handover planned for Dec 2026. The escrow account is at Dubai Islamic Bank (Public Joint Stock Company).
Schedule check
Build progress is 36 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Majan
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| The Haven Ii | Meraki Real Estate Development | 56% | AED 1.02M | 1,260 | 62 |
| The Haven | Meraki Real Estate Development | Ready | AED 1.05M | 1,447 | 102 |
| Divine Al Barari | Takmeel Real Estate Development | 20% | AED 1.11M | 1,382 | 100 |
| Tulip Oasis 11 | A M E Real Estate Development | 93% | AED 1.18M | 1,290 | 76 |
| Lazord By Lapis | Lapis Properties | 28% | AED 729K | 1,453 | 61 |
| Barari Palace | Ary & Maz Development | 0% | AED 1.04M | 1,568 | 60 |
| Rijas Suites | Dusit Rijas Properties | 3% | AED 623K | 1,888 | 59 |
Other projects by Meraki Real Estate Development
Questions buyers ask
How much does a home in The Haven II cost?
The median DLD sale price is AED 1.02M (AED 1,260 per sqft), from 62 sales in the last 12 months. The middle half of sales ran from AED 976,540 – AED 1.39M.
When is the handover of The Haven II?
The DLD registry shows a planned completion date of Dec 2026. Build progress is 56%. Build progress is 36 pts behind the share of time used.
Who is the developer of The Haven II?
Meraki Real Estate Development. The DLD registry lists 3 projects by this developer, 1 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Majan from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.