Rijas Suites
Under constructionby Dusit Rijas Properties · Majan
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Rijas Suites is AED 623,029 (AED 1,888 per sqft), 28% above the Majan median of AED 1,480 per sqft, from 59 sales in the last 12 months. It is 3% built, with handover planned for Dec 2028. The escrow account is at United Bank Limited (Management Office).
Schedule check
Build progress is 43 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Majan
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Rijas Suites | Dusit Rijas Properties | 3% | AED 623K | 1,888 | 59 |
| Divine Al Barari | Takmeel Real Estate Development | 20% | AED 1.11M | 1,382 | 100 |
| Tulip Oasis 11 | A M E Real Estate Development | 93% | AED 1.18M | 1,290 | 76 |
| The Haven Ii | Meraki Real Estate Development | 56% | AED 1.02M | 1,260 | 62 |
| Lazord By Lapis | Lapis Properties | 28% | AED 729K | 1,453 | 61 |
| Barari Palace | Ary & Maz Development | 0% | AED 1.04M | 1,568 | 60 |
| Samana Barari Lagoons | Samana Signature Real Estate Developments | 17% | AED 1.21M | 1,614 | 59 |
Questions buyers ask
How much does a home in Rijas Suites cost?
The median DLD sale price is AED 623,029 (AED 1,888 per sqft), from 59 sales in the last 12 months. The middle half of sales ran from AED 602,429 – AED 859,748.
When is the handover of Rijas Suites?
The DLD registry shows a planned completion date of Dec 2028. Build progress is 3%. Build progress is 43 pts behind the share of time used.
Who is the developer of Rijas Suites?
Dusit Rijas Properties. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Majan from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.