The Central Downtown
Under constructionby Aqua Properties · Arjan
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in The Central Downtown is AED 1.08M (AED 1,425 per sqft), 9% below the Arjan median of AED 1,561 per sqft, from 145 sales in the last 12 months. It is 11% built, with handover planned for Mar 2028. The escrow account is at First Abu Dhabi Bank P.J.S.C..
Schedule check
Build progress is 57 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Arjan
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| The Central Downtown | Aqua Properties | 11% | AED 1.08M | 1,425 | 145 |
| Binghatti Hillcrest | Binghatti Developers | 60% | AED 1.00M | 2,170 | 235 |
| Butterfly | Desert Falcon Real Estate Development | 8% | AED 1.32M | 1,669 | 211 |
| Enchante By Grid | Grid Viv Real Estate Development | 0% | AED 699K | 1,763 | 156 |
| One Beverly | H M B Homes Real Estate Development | 73% | AED 750K | 1,618 | 135 |
| Empire Estates | Empire Real Estate Developments | 60% | AED 1.28M | 1,714 | 100 |
| Oxford Gardens | Iman Developers | Ready | AED 840K | 1,817 | 68 |
Other projects by Aqua Properties
Questions buyers ask
How much does a home in The Central Downtown cost?
The median DLD sale price is AED 1.08M (AED 1,425 per sqft), from 145 sales in the last 12 months. The middle half of sales ran from AED 790,638 – AED 1.44M.
When is the handover of The Central Downtown?
The DLD registry shows a planned completion date of Mar 2028. Build progress is 11%. Build progress is 57 pts behind the share of time used.
Who is the developer of The Central Downtown?
Aqua Properties. The DLD registry lists 2 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Arjan from a RERA-licensed specialist.