Binghatti Cullinan
Under constructionby Binghatti Developers · Sama Al Jadaf, Al Jaddaf
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Binghatti Cullinan is AED 1.45M (AED 2,199 per sqft), in line with the Sama Al Jadaf, Al Jaddaf median of AED 2,185 per sqft, from 506 sales in the last 12 months. It is 0% built, with handover planned for Jun 2027. The escrow account is at United Arab Bank.
Schedule check
Build progress is 56 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Sama Al Jadaf, Al Jaddaf
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Binghatti Cullinan | Binghatti Developers | 0% | AED 1.45M | 2,199 | 506 |
| Azizi David | Azizi Developments | 2% | AED 838K | 2,365 | 139 |
| J188 | Jad Global Real Estate Development | 0% | AED 1.25M | 1,600 | 67 |
Other projects by Binghatti Developers
Binghatti VintageBinghatti Skyflame 1Binghatti TitaniaBinghatti SkyriseBinghatti HillsBinghatti Apex
Projects at a similar price
Binghatti PhantomSobha Hartland Greens - Phase IiiLuma Park ViewsRoyal Regency SuitesWindsor House
Projects anywhere in Dubai with the closest median sale price.
Questions buyers ask
How much does a home in Binghatti Cullinan cost?
The median DLD sale price is AED 1.45M (AED 2,199 per sqft), from 506 sales in the last 12 months. The middle half of sales ran from AED 866,999 – AED 1.56M.
When is the handover of Binghatti Cullinan?
The DLD registry shows a planned completion date of Jun 2027. Build progress is 0%. Build progress is 56 pts behind the share of time used.
Who is the developer of Binghatti Cullinan?
Binghatti Developers. The DLD registry lists 44 projects by this developer, 14 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Sama Al Jadaf, Al Jaddaf from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.