Terra Gardens
Under constructionby Dwtc Emaar · Dubai World Central
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Terra Gardens is AED 1.64M (AED 2,114 per sqft), 25% above the Dubai World Central median of AED 1,697 per sqft, from 543 sales in the last 12 months. It is 0% built, with handover planned for Oct 2029. The escrow account is at Dubai Islamic Bank (Public Joint Stock Company).
Schedule check
Build progress is 14 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai World Central
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Terra Gardens | Dwtc Emaar | 0% | AED 1.64M | 2,114 | 543 |
| Azizi Venice 7 | Azizi Developments | 29% | AED 670K | 1,857 | 694 |
| Azizi Venice 13 | Azizi Developments | 46% | AED 655K | 1,676 | 669 |
| Azizi Venice 12 | Azizi Developments | 22% | AED 725K | 1,685 | 632 |
| Azizi Venice 11 | Azizi Developments | 26% | AED 675K | 1,667 | 448 |
| Azizi Venice 9 | Azizi Developments | 54% | AED 699K | 1,881 | 335 |
| Azizi Venice 16 | Azizi Developments | 0% | AED 751K | 1,898 | 293 |
Other projects by Dwtc Emaar
Questions buyers ask
How much does a home in Terra Gardens cost?
The median DLD sale price is AED 1.64M (AED 2,114 per sqft), from 543 sales in the last 12 months. The middle half of sales ran from AED 1.58M – AED 2.38M.
When is the handover of Terra Gardens?
The DLD registry shows a planned completion date of Oct 2029. Build progress is 0%. Build progress is 14 pts behind the share of time used.
Who is the developer of Terra Gardens?
Dwtc Emaar. The DLD registry lists 3 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Dubai World Central from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.