Solara Tower Dubai
Under constructionby S O L Properties Development · Downtown Dubai
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Solara Tower Dubai is AED 7.20M (AED 3,705 per sqft), 22% above the Downtown Dubai median of AED 3,030 per sqft, from 52 sales in the last 12 months. It is 21% built, with handover planned for Aug 2027. The escrow account is at Emirates Nbd Bank (P.J.S.C).
Schedule check
Build progress is 52 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Downtown Dubai
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Solara Tower Dubai | S O L Properties Development | 21% | AED 7.20M | 3,705 | 52 |
| Act One | Act Two | Emaar Development | Ready | AED 2.78M | 3,052 | 54 |
| Burj Crown | Emaar Development | Ready | AED 2.63M | 2,804 | 50 |
| Binghatti Skyblade | Binghatti Developers | 17% | AED 1.94M | 3,909 | 567 |
| One Residence | Ginco Properties | 6% | AED 2.28M | 2,930 | 74 |
| Forte | Emaar Development | Ready | AED 3.30M | 2,880 | 72 |
| Grande | Emaar Development | Ready | AED 4.75M | 3,238 | 63 |
Other projects by S O L Properties Development
Questions buyers ask
How much does a home in Solara Tower Dubai cost?
The median DLD sale price is AED 7.20M (AED 3,705 per sqft), from 52 sales in the last 12 months. The middle half of sales ran from AED 5.97M – AED 8.62M.
When is the handover of Solara Tower Dubai?
The DLD registry shows a planned completion date of Aug 2027. Build progress is 21%. Build progress is 52 pts behind the share of time used.
Who is the developer of Solara Tower Dubai?
S O L Properties Development. The DLD registry lists 3 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Downtown Dubai from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.