Rivo
Under constructionby Grovy Homes Real Estate Development · Dubai Land Residence Complex
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Rivo is AED 1.02M (AED 1,227 per sqft), 13% below the Dubai Land Residence Complex median of AED 1,417 per sqft, from 82 sales in the last 12 months. It is 7% built, with handover planned for Dec 2027. The escrow account is at Mashreq Bank Psc.
Schedule check
Build progress is 38 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai Land Residence Complex
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Rivo | Grovy Homes Real Estate Development | 7% | AED 1.02M | 1,227 | 82 |
| The Corner | Arabian Gulf Properties | 38% | AED 1.11M | 1,089 | 95 |
| Verdania 1 | Obj1 Real Estate Development | 17% | AED 741K | 1,383 | 91 |
| Cove Edition Residence 5 By Imtiaz | Imtiaz Real Estate Investment & Development | 26% | AED 686K | 1,723 | 86 |
| Arlington Park By Majid | Majid Developments | 6% | AED 727K | 1,579 | 78 |
| Khk 31 | Khk Realestate Development | 26% | AED 605K | 1,582 | 71 |
| Celesto Tower 2 | Tarrad Development | 0% | AED 784K | 1,460 | 69 |
Questions buyers ask
How much does a home in Rivo cost?
The median DLD sale price is AED 1.02M (AED 1,227 per sqft), from 82 sales in the last 12 months. The middle half of sales ran from AED 952,000 – AED 1.15M.
When is the handover of Rivo?
The DLD registry shows a planned completion date of Dec 2027. Build progress is 7%. Build progress is 38 pts behind the share of time used.
Who is the developer of Rivo?
Grovy Homes Real Estate Development. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Dubai Land Residence Complex from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.