Minati Homes 1
Under constructionby Januss Real Estate Developers · Al Furjan
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Minati Homes 1 is AED 1.61M (AED 1,391 per sqft), in line with the Al Furjan median of AED 1,400 per sqft, from 54 sales in the last 12 months. It is 51% built, with handover planned for Sept 2026. The escrow account is at First Abu Dhabi Bank P.J.S.C..
Schedule check
Past planned date by about 1 months.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Al Furjan
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Minati Homes 1 | Januss Real Estate Developers | 51% | AED 1.61M | 1,391 | 54 |
| Azizi Zain | Azizi Developments | 80% | AED 1.51M | 1,167 | 81 |
| 999 Residences By Reef Luxury Development | Reef Luxury Development | 13% | AED 1.40M | 1,515 | 69 |
| Raffi By Azizi | Azizi Developments | 2% | AED 592K | 1,696 | 67 |
| Azizi Star Hotel Apartments | Azizi Developments | Ready | AED 525K | 1,282 | 58 |
| Azizi Plaza Hotel Apartments | Azizi Developments | Ready | AED 520K | 1,266 | 56 |
| Azizi Amir | Azizi Developments | 2% | AED 1.54M | 1,501 | 54 |
Questions buyers ask
How much does a home in Minati Homes 1 cost?
The median DLD sale price is AED 1.61M (AED 1,391 per sqft), from 54 sales in the last 12 months. The middle half of sales ran from AED 1.50M – AED 1.87M.
When is the handover of Minati Homes 1?
The DLD registry shows a planned completion date of Sept 2026. Build progress is 51%. Past planned date by about 1 months.
Who is the developer of Minati Homes 1?
Januss Real Estate Developers. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Al Furjan from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.