Expo City Mangrove Residences
Under constructionby Expo City Mangrove Residences Development · Dubai World Central
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Expo City Mangrove Residences is AED 2.45M (AED 1,950 per sqft), 15% above the Dubai World Central median of AED 1,697 per sqft, from 60 sales in the last 12 months. It is 91% built, with handover planned for Jan 2026. The escrow account is at Dubai Islamic Bank (Public Joint Stock Company).
Schedule check
Past planned date by about 9 months.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai World Central
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Expo City Mangrove Residences | Expo City Mangrove Residences Development | 91% | AED 2.45M | 1,950 | 60 |
| Discovery Dunes | Dlc Ds Developer | 70% | AED 23.01M | – | 64 |
| Terra Heights | Dwtc Emaar | 9% | AED 2.21M | 2,000 | 64 |
| Hayat 3 | Dubai South Properties Dwc | 4% | AED 4.33M | 1,340 | 63 |
| Waada - Rayhan 1 | Bt Properties Dwc | 2% | AED 2.92M | 1,484 | 56 |
| Hayat 2 | Dubai South Properties Dwc | 2% | AED 4.40M | 1,426 | 55 |
| Azizi Venice 3 | Azizi Developments | 76% | AED 1.08M | 1,532 | 51 |
Questions buyers ask
How much does a home in Expo City Mangrove Residences cost?
The median DLD sale price is AED 2.45M (AED 1,950 per sqft), from 60 sales in the last 12 months. The middle half of sales ran from AED 1.96M – AED 2.78M.
When is the handover of Expo City Mangrove Residences?
The DLD registry shows a planned completion date of Jan 2026. Build progress is 91%. Past planned date by about 9 months.
Who is the developer of Expo City Mangrove Residences?
Expo City Mangrove Residences Development. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Dubai World Central from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.