Discovery Dunes
Under constructionby Dlc Ds Developer · Dubai World Central
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Discovery Dunes is AED 23.01M, from 64 sales in the last 12 months. It is 70% built, with handover planned for Dec 2023. The escrow account is at Mashreq Bank Psc.
Schedule check
Past planned date by about 35 months.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai World Central
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Discovery Dunes | Dlc Ds Developer | 70% | AED 23.01M | – | 64 |
| Golf Trails | Emaar Dubai South Dwc | 0% | AED 1.29M | 1,709 | 90 |
| Hayat 6 | Dubai South Properties Dwc | 0% | AED 5.10M | 1,454 | 87 |
| Waada - Cascada 2 | Bt Properties Dwc | 0% | AED 871K | 1,138 | 83 |
| Terra Heights | Dwtc Emaar | 9% | AED 2.21M | 2,000 | 64 |
| Hayat 3 | Dubai South Properties Dwc | 4% | AED 4.33M | 1,340 | 63 |
| Expo City Mangrove Residences | Expo City Mangrove Residences Development | 91% | AED 2.45M | 1,950 | 60 |
Questions buyers ask
How much does a home in Discovery Dunes cost?
The median DLD sale price is AED 23.01M, from 64 sales in the last 12 months. The middle half of sales ran from AED 1.36M – AED 33.05M.
When is the handover of Discovery Dunes?
The DLD registry shows a planned completion date of Dec 2023. Build progress is 70%. Past planned date by about 35 months.
Who is the developer of Discovery Dunes?
Dlc Ds Developer. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?