The median sale price in Burj Capital is AED 3.86M, from 140 sales in the last 12 months. It is 2% built, with handover planned for Dec 2028. The escrow account is at Emirates Islamic Bank P.J.S.C..
Schedule check
Build progress is 37 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Business Bay
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Burj Capital | Centurion Capital One Properties | 2% | AED 3.86M | – | 140 |
| Binghatti Skyrise | Binghatti Developers | 22% | AED 1.54M | 2,944 | 434 |
| One By Binghatti | Binghatti Developers | 50% | AED 3.07M | 2,938 | 212 |
| Damac Towers By Paramount | Damac Star Properties | Ready | AED 1.65M | 1,434 | 151 |
| Bay Square | Business Bay | Ready | AED 4.10M | 1,449 | 119 |
| One River Point | Dutco Ellington Canal Front Real Estate | 35% | AED 3.65M | 2,654 | 97 |
| Prive By Damac | Namaa Properties Development | Ready | AED 1.05M | 2,228 | 95 |
Projects at a similar price
Trump TowerThe St. Regis Residences, Downtown DubaiSoulever' By BeyondAddress Harbour PointHaven By Aldar 1
Projects anywhere in Dubai with the closest median sale price.
Questions buyers ask
How much does a home in Burj Capital cost?
The median DLD sale price is AED 3.86M, from 140 sales in the last 12 months. The middle half of sales ran from AED 3.01M – AED 5.37M.
When is the handover of Burj Capital?
The DLD registry shows a planned completion date of Dec 2028. Build progress is 2%. Build progress is 37 pts behind the share of time used.
Who is the developer of Burj Capital?
Centurion Capital One Properties. The DLD registry lists 1 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Business Bay from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.