Ember At Park Five
Under constructionby Deyaar Development · Dubai Production City
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Ember At Park Five is AED 1.10M (AED 1,339 per sqft), in line with the Dubai Production City median of AED 1,343 per sqft, from 117 sales in the last 12 months. It is 18% built, with handover planned for Jun 2027. The escrow account is at Dubai Islamic Bank (Public Joint Stock Company).
Schedule check
Build progress is 54 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai Production City
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Ember At Park Five | Deyaar Development | 18% | AED 1.10M | 1,339 | 117 |
| Soul By Vision | Vision Platinum Real Estate Development | 77% | AED 948K | 1,172 | 143 |
| Elm At Park Five | Deyaar Development | 16% | AED 1.07M | 1,327 | 137 |
| Sera Gardens By Vision | Clear Vision Real Estate Development | 0% | AED 953K | 1,510 | 136 |
| Neem At Park Five | Deyaar Development | 15% | AED 1.13M | 1,326 | 110 |
| Golf Terrace Residences By Asak | Asak Real Estate Development | 5% | AED 733K | 1,434 | 89 |
| The Crescent | Damac Properties Co | Ready | AED 450K | 832 | 84 |
Other projects by Deyaar Development
Downtown ResidencesIvy At Park FiveEleve By DeyaarElm At Park FiveNeem At Park FiveRegalia
Questions buyers ask
How much does a home in Ember At Park Five cost?
The median DLD sale price is AED 1.10M (AED 1,339 per sqft), from 117 sales in the last 12 months. The middle half of sales ran from AED 1.04M – AED 1.19M.
When is the handover of Ember At Park Five?
The DLD registry shows a planned completion date of Jun 2027. Build progress is 18%. Build progress is 54 pts behind the share of time used.
Who is the developer of Ember At Park Five?
Deyaar Development. The DLD registry lists 11 projects by this developer, 4 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Dubai Production City from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.