Avenew888-Loom
Under constructionby Avenew Real Estate Development · Dubai South
Updated 22 October 2026 · Source: DLD open data · Information, not financial advice. Not an official DLD product.
The median sale price in Avenew888-Loom is AED 1.03M (AED 1,429 per sqft), 5% above the Dubai South median of AED 1,360 per sqft, from 225 sales in the last 12 months. It is 2% built, with handover planned for Mar 2028. The escrow account is at Dubai Islamic Bank (Public Joint Stock Company).
Schedule check
Build progress is 25 pts behind the share of time used.
Progress gap compares build progress with the share of planned time already used. A project 40% built after using 60% of its planned time shows -20 pts.
Registry details
Compare with other projects in Dubai South
| Project | Developer | Status | Median price | Price / sqft | Sales |
|---|---|---|---|---|---|
| Avenew888-Loom | Avenew Real Estate Development | 2% | AED 1.03M | 1,429 | 225 |
| Mag 5 Boulevard | Mag 5 Property Development | Ready | AED 660K | 1,117 | 94 |
| Celestia | Damac Development | Ready | AED 540K | 1,118 | 85 |
| Windsor House Ii | Ellington Properties Development | 1% | AED 1.65M | 1,541 | 399 |
| Enre Residence By Imtiaz | Imtiaz South Real Estate Development | 15% | AED 1.36M | 1,571 | 125 |
| Avenew888 - Modo | Avenew Real Estate Development | 21% | AED 1.43M | 1,350 | 91 |
| Marquis Horizon | Marquis Home Developer | 0% | AED 1.28M | 1,580 | 75 |
Other projects by Avenew Real Estate Development
Questions buyers ask
How much does a home in Avenew888-Loom cost?
The median DLD sale price is AED 1.03M (AED 1,429 per sqft), from 225 sales in the last 12 months. The middle half of sales ran from AED 920,000 – AED 1.35M.
When is the handover of Avenew888-Loom?
The DLD registry shows a planned completion date of Mar 2028. Build progress is 2%. Build progress is 25 pts behind the share of time used.
Who is the developer of Avenew888-Loom?
Avenew Real Estate Development. The DLD registry lists 4 projects by this developer, 0 of them completed.
Ask before you buy off-plan
- Is the project registered with DLD and is the escrow account in the developer's name at the bank shown here?
- What share of the price must be paid before the developer allows resale?
- What does the sale agreement say about delay compensation and the latest handover date?
- Is the payment plan linked to construction milestones or to calendar dates?
Get help with Dubai South from a RERA-licensed specialist.
Source: DLD project registry and sales, via Dubai Data. Data through 22 October 2026. Registry dates can lag official extensions. Source · ZoneIQ gives information, not financial or investment advice. Figures are medians and estimates. Check any unit yourself before you commit.